- Completing the skeleton and concrete roof of 6 construction chambers at the head of the well
- Completion of foundation and wall concreting operations of 12 cast iron and polyethylene basins
- The end of the wall-laying operation of building room number one and the beginning of wall-laying of building room number two
- Installation of fittings and valves of 3 polyethylene line ponds
- Completion of drilling and piping operations of cast iron line inside the city, 650 meters long
- Continue the operation of plastering the ceiling of building rooms 1 to 5