Implementation of the Meybod project

cast iron line
- Concreting operation of the wall of a 400 line cast iron pond in 04+325 kilometers
Completion of the drilling operation of 400 meters long cast iron line in the inner city
- Completion of leveling and regulation of the channel floor of line 400 cast iron in the inner city, 900 meters long
- Piping operation of 400 cast iron line in the inner city, 650 meters long
- Dewatering operation of 400 cast iron line to perform test operation
Polyethylene line
— — Concreting operation of the wall of 2 ponds of the polyethylene line
— Reinforcement operation of the foundation and wall of a polyethylene line pond
- Start of bricklaying operation for the facade of new Sarchahi building No. 2
-Continuation of the plastering operation of the roof of the new Sarchahi building number 2