Zone 5
Completion of the hydrostatic test operation of Part 6 and verification by the monitoring device
Zone 3
- Pipe threading operations along the route of the 1000 line of Zone 3 from the mileage of 05+100 to 05+390 and from 06+730 to 07+215 for a total length of 775 meters
- Canal digging, leveling and pipe laying operations of the 1000 zone 3 line from 05+100 km to 05+390 km and from 06+730 to 07+215 total length of 775 meters
- Moving and transporting the soil of the opposite earth dam from 07+020 km to 07+300 km with a length of 280 meters.
- Moving and transporting excess soil from 06+735 km to 07+215 km with a length of 480 meters
- Earth embankment operation of Kemer Lule from 735+06 to 07+215 kilometers and from 05+110 to 05+390, total length of 760 meters
- The start of dewatering operation of the first and second part of the test
- Visit of Chabahar Free Zone Organization representatives.
Zone 5
- Implementation of the AX route of the executive channel of line 1200 inside the desalination plant
Zone 3
- Pipe threading operation along the route of line 1000 zone 3 from km 07+346 to 07+630 with a length of 284 meters
- Canal digging, leveling and piping operations of the 1000 line of zone 3 from 05+390 km to 05+582 km and from 07+215 to 07+538 total length of 516 meters
- Moving and transporting the soil of the opposite earth embankment from the mileage of 07+330 to 07+555 with a length of 225 meters
- The final embankment operation on the pipe from km 05+390 to 05+582 with a length of 192 meters
- Continuation of water extraction operation part 1 test line 1000 zone 3 from 020+00 km to 740+00 km with a length of 720 meters
- Entry and discharge of 12 pipe services of size 1000 in zone 3 with 72 branches