- Surveying operations from km 000+00 to 252+01 (entire route)
- Drilling operations for the entire route
- Leveling and regulating the canal floor (entire route)
- Installation of 600 mm GRP pipe from km 000+00 to 252+01 (entire route)
- Drilling and implementation of 168 m long steel CASING
- Backfilling on GRP pipes from km 00+0 to 252+01
- Construction of 5 ponds out of a total of 5 ponds