Project status at a glance
Project Title:
The implementation of the water transmission line from the existing wells to the 10,000 cubic meter reservoir, construction, drilling and supplementary works of wells and wellhead facilities and the construction of an access road
contract number:
1401/Q/(1401/25/8783)001
Agreement date:
2023.01.07
Contract period:
18 months
Main employer:
Yazd Province Water and Wastewater Company
Employer:
Farsan Industrial Production Company
Contractor:
Hamoon Pipeline Development Company