Birjand

Project: Water supply and operation for Birjand drinking water treatment plant

Scope of work: procurement and strategic management of Birjand drinking water treatment plant, evaluation of the chemicals consumed by the units, technical and performance checkup of  all the mechanical systems in the treatment plant, including the automation systems, electrical systems, hydraulic and pneumatic systems testing chemicals, plant software (PLC), plumbing status for smooth operation of the plant.

 

Employer: South Khorasan Regional Water Company

Construction Consultant and Supervisor: Deputy of Protection and Exploitation

Contractor: Hamoon Pipeline Development Company

Duration of Contract 18 months