The progress of the sewage pump house project No. 23, Imam Khomeini port

8
  • Closing the electric pole equipment, installing the electric pole and transferring the electric network to it
  • Installation of shed windbreaks, welding and installation of roof crane supports
  • Cabling of flowmeters, pumps, ventilators and electric crane and installation of cable tray cover
  • Drilling the number one and two connectors
  • Pump panel cabling
  • Installation of garbage baskets