The operational progress of the Meibod pipeline and 10,000 cubic meter reservoir project

  • Completion of 3.775-5.825 kilometer drilling operations with a length of 2050 meters and implementation of ductile iron piping operations with a length of 1950 meters.
  • Completion of 4290 meters long drilling operations and 3000 meters long polyethylene piping operations.
  • Completion of foundation reinforcement of new wells No. 1 and 2 and regional water emergency well No. 
  • Completion of concreting the foundation of new wells number 1 and 2