Qarchak Industrial Town Project

  • Completion of piping of water and sewage network in zone 4
  • Progress of 90% of the water distribution network and wastewater collection phase 2 of Qarchak Industrial Town
  • Progress of 70% of the water transmission line from phase 1 to phase
  • Completion and construction of sewage manholes and tap basins in zones 1 to 5
  • Progress of 30% of the sewage transfer line from phase 2 to the site of the treatment plant