Executive operations of the Baheri project

Actions:

  • Completion of the reinforcement and molding of the roof of the tank part 4 and 8 (ready for concreting)
  • Mapping and implementation of foundation heel points
  • The start of the reinforcement of part 25 of the foundation
Entry of materials:
  • Arrival of 5 tons of scaffolding in the workshop
  • The arrival of 100 tons of size 20 rebar to the workshop