Executive operations of Khave project

Actions:

  • Completion of reinforcement, molding and concreting of the column of the first floor of the guard building
  • Reinforcement and molding of the roof of the first floor (80% physical progress)
  • Start of construction of concrete tank ladders (20% physical progress)
  • Continuing the construction of the foundations of the air tank (50% physical progress)
Entry of materials:
  • Unolite roof
  • Rebar without tread (air tank)