Mahshahr project progress report

  • 55% progress of the whole project
  • Supply of pumps and equipment and construction of burying tank of pumping station No. 16
  • 90% progress of the piping operation of the output line of pumping station No. 16
  • Electrical and mechanical equipment and removal of structural defects of pumping station number 2