Executive operations on the project are advancing at a favorable pace, with the 20,000-cubic-meter Baheri concrete reservoir currently reaching 80% physical progress. Aimed at increasing storage capacity and upgrading water supply infrastructure, the project is now in its final stages of execution.
Simultaneously, the installation of precast concrete perimeter walls is underway. Designed to improve, secure, and organize the site, the use of precast components enhances construction speed while ensuring superior structural quality and durability.
Work continues to align with the project timeline, and its completion will mark a significant milestone in advancing the project’s infrastructure.