Project for Supply and Installation of GRP Water Transmission Pipeline to Saba Foulad Khalij Fars Plant (Bandar Abbas)
- Technical Specifications:
Installation of a water transmission pipeline using 600 mm diameter GRP pipes, Bi-axial type, with rigid joints executed by lamination method. - Project Schedule:
- Commencement of construction works: February 2024
- Completion of construction works: May 2025 (including minor defect rectifications)
- Current Project Status:
Provisional handover has been completed and the project has entered the Defects Liability Period (DLP).